Mount Utsayantha Project Implementation

2003

  • November
    Start organizing for implementation; establish subcommittees; assign tasks.
  • December
    Start formal fundraising efforts locally - focus on fire tower as first phase.

    Submit application to Robinson-Broadhurst for observation building.

2004

  • April
    Submit grant applications to O'Connor & CWC for observation building.
  • May
    Organize volunteer work day - clean up park, make initial repairs to building.
  • June
    Begin work on fire tower restoration; install signage.
  • July
    Submit grant application to OPRHP for park development & acquisition.
  • August
    Fire Tower reopens& new trail is dedicated.
  • November
    Apply for recreational trails grant.

2005

  • May
    Restoration of observation building begins.
  • June
    Park development work begins (pending funding approval).
  • July
    Begin work on access road

2006

  • June
    Observation building reopens on 80-year anniversary.
  • September
    Park development work completed.